Excerpt: "Many of these 15 'near misses' occurred because reactor owners either tolerated known safety problems or took inadequate measures to correct them, Lochbaum finds. For example, the owner of the Oconee nuclear plant in South Carolina installed a backup reactor core cooling system in 1983. However, in 2011 - more than a quarter-century later - workers discovered a problem with the system that would have rendered it useless in an accident."
America's worst nuclear accident to date occurred at Three Mile Island, seen here on March 15, 2011. (photo: Jonathan Ernst/Reuters)
Fifteen 'Near-Misses' at US Nuclear Plants in 2011
29 February 12
ASHINGTON, DC, February 28, 2012 (ENS) - The Union of Concerned Scientists has documented 15 "near-misses" at 13 U.S. nuclear plants during 2011 and evaluates the response of the Nuclear Regulatory Commission to each event in a report released today.
The second in an annual series of reports, "The NRC and Nuclear Power Plant Safety 2011 Report: Living on Borrowed Time" details 15 special inspections launched by the federal agency in response to problems with safety equipment, security shortcomings, and other troubling events at nuclear power plants.
The overview is provided by David Lochbaum, the director of UCS's Nuclear Safety Project. He worked at U.S. nuclear plants for 17 years and was a boiling water reactor technology instructor for the Nuclear Regulatory Commission.
"While none of the safety problems in 2011 caused harm to plant employees or the public, their frequency - more than one per month - is high for a mature industry," Lochbaum writes.
NRC inspectors examine equipment at the Salem nuclear power plant in New Jersey. (Photo courtesy UCS) |
In the 40 years that the Union of Concerned Scientists has evaluated safety at U.S. nuclear power plants, "We have repeatedly found that NRC enforcement of safety regulations is not timely, consistent or effective," the report states.
The UCS says its findings match those of the agency's internal assessments, as well as of independent agents such as the NRC's Office of Inspector General and the federal Government Accountability Office, which is the investigative arm of Congress.
Many of these 15 "near misses" occurred because reactor owners either tolerated known safety problems or took inadequate measures to correct them, Lochbaum finds.
For example, the owner of the Oconee nuclear plant in South Carolina installed a backup reactor core cooling system in 1983. However, in 2011 - more than a quarter-century later - workers discovered a problem with the system that would have rendered it useless in an accident.
Another significant safety-related event in 2011 occurred at the Braidwood and Byron nuclear plants in Illinois. Workers at those plants had instituted a practice in 1993 of deliberately draining water from the piping to a vital safety system. They did so to reduce corrosion caused by the drawing of untreated lake water into the system. However, writes Lochbaum, "their solution would have prevented this vital safety system from functioning properly during an accident."
In addition to "near misses" at these three nuclear plants, 12 others are documented in the report.
Palisades nuclear power plant on the shore of Lake Michigan, where two "near-misses" occurred in 2011 (Photo courtesy NRC) |
Exelon's Lasalle nuclear power plant 75 miles southwest of Chicago, Illinois (Photo courtesy Exelon) |
At the LaSalle plant in Illinois, owned and operated by Exelon, NRC inspectors challenged operators' practice of leaving a test tank partially filled with water. Safety studies of what would happen at the plant during an earthquake assumed that this tank would be empty, because workers were supposed to fill it with water only during infrequent testing.
NRC inspectors questioned whether the weight of the water in the tank could cause it to collapse or topple during an earthquake. After an analysis confirmed their suspicions, workers at LaSalle drained the tank and revised procedures to keep it empty except during testing.
The NRC's catch at LaSalle led workers at the Duane Arnold nuclear plant in Iowa operated by NextEra Energy Resources to discover and correct the same problem.
While Lochbaum praises the NRC for catching these specific problems, he is critical of more generalized agency policies.
"The NRC's insistence that 47 reactors are safe enough to continue operating despite their continued failure to comply with fire protection regulations does not stand up to legal or ethical scrutiny," he writes in the report.
"Similarly," writes Lochbaum, "the NRC continues to allow 27 plants to operate with seismic protection levels inadequate to meet seismic threat levels, even though it has been aware of the problem for over a decade. Making matters worse, eight plants have inadequate protection from both fire and earthquake."
More technical, but just as troubling is the problem with "component design basis inspections."
Each nuclear plant periodically undergoes component design basis inspections, or CDBIs, to ensure that owners are operating and maintaining their reactors within specifications approved during design and licensing.
The Nuclear Regulatory Commission: from left: William D. Magwood IV, Kristine Svinicki, Chairman Gregory Jaczko, George Apostolakis, William Ostendorff (Photo courtesy NRC) |
In 2011, NRC inspectors identified numerous problems with reactor safety components and operating procedures during CDBIs, Lochbaum points out. Some of the problems concerned containment vent valves, battery power sources, and emergency diesel generators - components that affected the severity of the March 2011 disaster at Tokyo Electric Power Co's Fukushima Daiichi nuclear plant in Japan.
"While it was good that the NRC identified these problems, each CDBI audits only a very small sample of possible trouble spots," writes Lochbaum.
For example, the CDBI at the Harris nuclear plant in North Carolina examined just 31 safety-related items among literally thousands of candidates. That audit found 10 problems.
"Beyond ensuring that the plant's owner corrected those 10 problems, the NRC should have insisted that it identify and correct inadequacies in the plant's testing and inspection regimes that allowed these problems to exist undetected in the first place," writes Lochbaum. "The true value of the CDBIs stems from the weaknesses they reveal in the owners' testing and inspection regimes. But that value is realized only when the NRC forces owners to remedy those weaknesses."
"A lack of improvement in CDBI results over time indicates a failure to address root causes," writes Lochbaum. "The NRC is treating the symptoms, but not the disease."
For its part, the industry is taking steps to bolster safety conditions at the nation's 104 operating nuclear power plants.
The Nuclear Energy Institute, an industry association, announced on February 21 the industry's "unanimous approval of an initiative to procure additional on-site portable equipment that will be available to help ensure that every commercial nuclear energy facility can respond safely to extreme events, no matter what the cause."
The initiative commits every company operating a nuclear energy facility to order or enter into contract for a plant-specific list of emergency equipment by March 31.
The equipment ranges from diesel-driven pumps and electric generators to ventilation fans, hoses, fittings, cables and communications gear. It includes support materials for emergency responders, including food, water and other supplies.
The equipment will supplement emergency equipment acquired by the industry in recent months and after the 9/11 terrorist attacks to help facilities safely respond to large fires and explosions.
"The additional portable equipment will provide power and water to maintain three key safety functions in the absence of AC power and heat transfer capability from permanently installed safety systems," said Tony Pietrangelo, the Nuclear Energy Institute's senior vice president and chief nuclear officer.
The three functions to be maintained are reactor core cooling, used fuel pool cooling and containment integrity.
Pietrangelo said the new equipment will be stored at diverse locations and protected to ensure that it can be used if other systems that comprise a facility's multi-layered safety strategy are compromised.
THE NEW STREAMLINED RSN LOGIN PROCESS: Register once, then login and you are ready to comment. All you need is a Username and a Password of your choosing and you are free to comment whenever you like! Welcome to the Reader Supported News community. |